-
The Day I Learned Elevators Aren't One-Size-Fits-All
-
Mistake #1: Trusting Specs Without Verifying Clearances
-
Mistake #2: Forgetting About Door Types
-
Mistake #3: Ignoring the Valve Stem Specs
-
Mistake #4: Assuming All KONE Models Are the Same (Spoiler: They're Not)
-
Mistake #5: Relying on Old Plans Without Checking Actual Construction
-
What I Use Now (The Checklist)
-
Final Thoughts
The Day I Learned Elevators Aren't One-Size-Fits-All
It was a Tuesday afternoon in early March 2023 when I got the call that made my stomach drop.
"We've got a problem with the KONE elevator shaft," the site foreman said. "It's too tight. The car dimensions don't match the opening."
I froze. See, I'd okayed the plans myself. I'd looked at the brochure specs for the KONE MiniSpace™, compared them to the architect's drawings, and given the thumbs up. What I hadn't done—what I learned that day I needed to do—was check the actual clearances against the final construction measurements.
Long story short: we ended up paying $3,200 in additional framing costs plus a 2-week delay. My boss didn't yell. He just looked at me with that disappointed face and said, "Next time, check everything."
That was my wake-up call. So I created a pre-check list. And in the 18 months since, I've caught 47 potential errors using it—some small, some that would've been expensive disasters.
Here's what I learned the hard way, and what I now use to avoid repeating the mistake.
Mistake #1: Trusting Specs Without Verifying Clearances
What I assumed: That the KONE MiniSpace dimensions on the cut sheet were the final word.
Reality check: The spec sheet gives the car interior dimensions. But the shaft opening requirements? Those often need to include tolerances, guide rails, door frames, and ventilation. I'd mentally added a few inches for wiggle room—but in that case, the constructed shaft was 1.5 inches narrower at one point thanks to a concrete pour that wasn't perfectly square.
Lessons learned:
- Always get the final, measured dimensions of the shaft—not just the planned ones
- Compare against the required clearances in the product manual, not the car size
- If the shaft is even 1% smaller than spec, flag it. Don't assume it'll fit
I still kick myself for not doing this. The fix cost $890 in rework plus the one-week delay.
Mistake #2: Forgetting About Door Types
What I assumed: Elevator doors are elevator doors. Same dimensions, same swing.
Reality check: Ever heard of a pocket door? It's a door that slides into the wall cavity. Common in tight spaces. But the pocket needs depth—usually 4-6 inches. And if you're retrofitting a KONE elevator into an existing shaft, you might not have that pocket space.
I once ordered 50 KONE spare parts—valve stems and door assemblies—only to find out the door frames were too wide for the pocket depth. Straight to the trash. $450 wasted.
Now I check:
- Door type (center opening, side opening, pocket door)
- Required door pocket depth
- Swing direction for the doors on each floor (yes, they can differ)
Don't hold me to this, but I'd estimate that about 20% of the errors I've caught since then are door-related. It's a bigger deal than people think.
Mistake #3: Ignoring the Valve Stem Specs
This one sounds technical, but stick with me.
When you order a KONE elevator, the hydraulic system relies on valve stems to control fluid flow. The thread size matters. So do the pressure ratings.
I once ordered a batch of 200 valve stems for a maintenance contract. They looked identical to the ones we'd used before. But the thread pitch was off by 0.5mm. Not enough to see with the naked eye, but enough that they wouldn't seal correctly.
The surprise wasn't the cost of the valve stems. It was the cost of the emergency repair when a stem failed on a Friday afternoon. Three techs, two hours of overtime, and a pissed-off building manager. That one mistake cost us $3,200 in repairs and service credits.
What I do now:
- Verify thread type and size against the original part number
- Check pressure rating specs (don't assume standard is adequate)
- Compare the replacement part against a known-good sample—physically, not just on paper
From my perspective, this is the single most overlooked detail in elevator maintenance ordering. Take it with a grain of salt, but I've seen it bite three different vendors in the last year.
Mistake #4: Assuming All KONE Models Are the Same (Spoiler: They're Not)
What I assumed: The KONE MiniSpace and KONE NanoSpace are basically the same with different names.
Reality check: The KONE NanoSpace is a machine room-less (MRL) elevator that uses the Ecodisc® motor. The MiniSpace is also an MRL, but the shaft dimensions, car sizes, and door types differ. The NanoSpace is designed for smaller shafts—often 10-12 inches narrower. The MiniSpace needs more room for the counterweight.
When I compared the two side by side—same number of floors, same passenger capacity—I finally understood why the specs matter so much. Using the wrong model for the shaft space is like trying to fit a size 11 foot into a size 10 shoe. You can force it, but it's going to hurt.
Checks I now run:
- Verify the model number is appropriate for the shaft dimensions
- Check for machine-room requirements (MRL vs. machine room)
- Look up the counterweight clearance specs for the model
In my opinion, you should never order an elevator without physically measuring the shaft first. Specs alone aren't enough.
Mistake #5: Relying on Old Plans Without Checking Actual Construction
What I assumed: The architect's drawing from 2022 is the same as what the contractor built in 2023.
Reality check: Construction changes happen. A beam gets shifted, a wall gets framed 2 inches thicker, a utility chase takes up space. By the time the elevator goes in, the shaft dimensions could be different from the plans.
Never expected this to be such a big deal. Turns out, you can't just order based on the architect's dimensions and trust that the contractor built exactly to spec. Especially in older buildings—the kind that need a KONE evolution or modernization package—the original shaft might not be square, plumb, or even vertical.
What my checklist now includes:
- A site walkthrough before ordering the elevator
- Confirmation that the shaft dimensions match the final as-built drawings
- A "last look" before the elevator is delivered—just in case
The surprise wasn't the wrong dimensions. It was how often the contractor had made undocumented changes. We caught 7 such cases in the last 18 months. Each one would have been a major redo.
What I Use Now (The Checklist)
Here's the simple pre-order checklist I use for every KONE elevator or escalator order. It's not fancy. But it works.
- Confirmed shaft dimensions (actual field measurement, not plan dimensions)
- Elevator model verified (MiniSpace vs. NanoSpace vs. MonoSpace)
- Door type and pocket depth confirmed (including swing direction per floor)
- Valve stem specs confirmed (thread type, pressure rating, part number)
- As-built drawings reviewed (for any undocumented changes)
I'm not 100% sure this covers every edge case, but it's caught 47 errors in 18 months. In my opinion, that's a pretty good track record for a $0 checklist.
Final Thoughts
If you're dealing with elevator specifications—whether it's for a new building, a modernisation project, or just ordering a spare part—don't assume anything. The details that seem minor (like a 0.5mm thread pitch difference) can become expensive problems.
Personally, I recommend this checklist for anyone handling elevator orders. But if you're dealing with a rush order and don't have time for a site visit, you might want to add an extra margin of error to your measurements. Better to order slightly bigger than necessary than to find out the hard way that the shaft is 2 inches too narrow.
And if you ever find yourself staring at a wall you just paid to have reframed because you didn't check the pocket door depth—well, welcome to the club. We've got a checklist for that.